• Update for our New Spiritual Home!

    Thank you all for your continued support and prayers! It’s been a long haul but we know that all is working out for our Highest and Best Good!

    Here are some updates:

    2017 – We’ve found a location that fits all of our needs – plenty of parking, no stairs to climb (1 level), plenty of room to accomodate our congregation and room to grow, centrally located to all those we serve, and so much more.

    2017 – We’ve signed the lease agreement for our new location and the deposit was accepted.

    11/08/17 – We were granted a Conditional Use Permit (CUP) by the city of Fullerton to operate a church service in our new space.

    01/08/18 – Some demolition has been started and construction of interior improvements to begin pending construction permit.

    Projected move in date – mid March 2018! Whoo hoo! Please keep praying 🙂